Value Stream Analysis

Value stream analysis, also called value stream mapping, comes from lean management and shows how a work item moves through a process step by step. For each step the team records how long people work on it and how long the work waits before the next step starts. Both times add up to the lead time and give the flow efficiency. Here you add the steps together in your browser and see in real time where work waits and for how long.

How it works

  1. Create a board and share the link with the team.
  2. Pick the time unit and enter the steps from order to delivery in sequence.
  3. Enter the processing time of each step and the waiting time until the next step.
  4. Look at the marked longest wait in the timeline and discuss how to shorten it.
  5. Download the result as CSV.

When should you use a value stream analysis?

You use a value stream analysis when a work item takes a long time and nobody can say exactly where the time goes. Typical occasions are a change request that needs weeks until delivery, an onboarding with many handovers or an approval chain across several departments. The method comes from the Toyota Production System and was developed in manufacturing. Mike Rother and John Shook described it in 1999 in the book Learning to See. Today teams apply it to software, administration and services.

It adds little for work that is done in one sitting or for processes that happen only once. A dispute about the quality of individual results also belongs elsewhere, because the analysis measures time and not quality. It gives the team a shared basis for the question of where an improvement pays off most.

What do processing time, waiting time, lead time and flow efficiency mean?

Processing time is the time someone actively works on a work item. Waiting time is the time the item sits after a step until the next step begins. The team enters both for each step, together with the name of the step and the role that performs it. The board calculates in one shared unit that you pick at the top: minutes, hours or days.

Lead time is the sum of all processing and waiting times, which means the duration from the first step to delivery. Flow efficiency puts the total processing time in relation to the lead time and reports the result as a percentage: flow efficiency equals total processing time divided by lead time times 100.

An example of the calculation: if a process involves 6 days of work and 16 days of waiting, the lead time is 22 days and the flow efficiency is 27.3 percent. The tool does not distinguish between value adding and other work. Every minute of processing time counts the same.

What does a value stream analysis look like in practice?

The example is invented. A team examines how a change request moves from intake to delivery. All times are in days. The totals show 6 days of processing against 16 days of waiting. The longest wait is 6 days before the technical review. The team starts there because shortening it lowers the lead time the most. If a fixed review slot every Tuesday cuts this wait to 2 days, the lead time drops to 18 days and the flow efficiency rises to 33.3 percent.

StepRoleProcessing in daysWait afterward in days
Capture requestBusiness unit0.53
Technical reviewArchitecture16
ApproveManagement0.254
ImplementDevelopment32
TestQuality assurance11
DeliverOperations0.250
Total616

How do you facilitate a value stream analysis?

A value stream analysis works when the people in the room carry out the process themselves. In a remote setting one person opens the board and shares the link. Everyone else adds the steps they know in real time. A moderator keeps the order of the steps in check.

  • Define start and end: the first step is the arrival of the request, the last one is delivery.
  • Enter the steps the way a work item moves through them, even if the official process looks different.
  • Let each role estimate its own time. The person who performs a step knows its processing and waiting time best.
  • Ask for every wait what the item waits for: a person, an approval, a date or a tool.
  • Discuss the marked longest wait first and collect ideas there before you tackle the next one.
  • Replace estimates with measured values later and compare the new lead time with the first version.

What mistakes happen in value stream analysis?

The most common mistake is forgetting the waiting time. Teams like to estimate how long they work on something and overlook the days in between. Yet the waiting time usually decides the lead time, as the example above shows. Enter it for every step, even when it is 0.

A second mistake is a cut that is too coarse or too fine. A step named Development hides waits inside development, while 40 single steps make the map unreadable. A dozen steps that each mark a handover has proven useful. The board accepts up to 50 steps.

A third mistake is treating flow efficiency as a target. It shows where waiting hides and says nothing about the quality of the work. Comparing teams with different kinds of work is misleading as well. A team is better off comparing itself with its own earlier state.

Value stream analysis or flowchart: what is the difference?

A flowchart shows the order of steps and decisions, whereas a value stream analysis shows the time a work item consumes along the way. The two views complement each other: the flowchart answers what happens in which sequence, the value stream analysis answers how long it takes and where it stalls.

AspectValue stream analysisFlowchart
Guiding questionWhere does the time go?How does the process run?
Content per stepProcessing time, waiting time, roleActivity and decision
BranchingNot provided, one path in sequenceYes, with decision diamonds
MetricsLead time and flow efficiencyNone
Typical useShortening long lead timesDocumenting and aligning

Key terms

Value stream
All steps a work item goes through from request to delivery to the customer.
Processing time
The time someone actively works on a step.
Waiting time
The time a work item sits after a step until the next one begins.
Lead time
The total duration of a work item from the first step to delivery. Here the sum of all processing and waiting times.
Flow efficiency
The share of processing time in the lead time, in percent. A low value indicates a lot of waiting.
Lean management
An approach that aligns processes with what benefits the customer and reduces waiting and waste. It goes back to the Toyota Production System.

Frequently asked questions

What is a value stream analysis?
A value stream analysis describes every step a work item goes through from request to delivery. The method comes from the Toyota Production System and is also known as value stream mapping. For each step you record the processing time and the waiting time after it. This shows where a work item sits idle instead of being worked on.
What does flow efficiency mean?
Flow efficiency is the share of processing time in the lead time, in percent. If a work item spends ten days in the process and is worked on for one of them, the flow efficiency is ten percent. Here the lead time is the sum of all processing and waiting times. To raise flow efficiency, start with the long waits the timeline marks.
How precise do the times need to be?
Team estimates are enough for a first analysis. All steps share one unit that you pick at the top of the board: minutes, hours or days. Times can be decimal numbers, for example 1.5 hours. Once you have measured values, replace the estimates and compare the new lead time with the first version.
Do participants need an account?
No. Anyone who opens the link enters a name or gets a random one and joins as a participant or as an observer. Participants add steps, change times and reorder the sequence. Observers see every change live and cannot change anything themselves. There is no registration and nothing to install.
What happens to the data after the session?
The steps live only in the room on the server. Once everyone has left, the room and all its content are deleted after a short time. To keep the result, download it as a CSV file beforehand. The file lists every step with role, processing time, waiting time and unit plus a total row and opens in Excel.
What is a good flow efficiency?
There is no fixed target because it depends on the process. A low value means work items sit more than they are worked on. It makes more sense to compare against your own starting value: if flow efficiency rises after a change, the waiting time has shrunk in relation to the work.
How do I find the bottlenecks in my process?
The bottleneck sits where a work item waits longest. The timeline on the board marks the longest wait. First ask what the item waits for there, for example an approval or a free person. Afterward look at steps with high processing time, in case the waits are small overall.
How do lead time and processing time differ?
Processing time is the time of active work. Lead time additionally contains all waiting times and is therefore the duration the customer experiences. An item with 6 days of processing and 16 days of waiting has a lead time of 22 days. A team can only shorten it when both times are recorded.
How many steps should a value stream analysis have?
Around five to fifteen steps are enough for most processes. A new step begins where work passes to another person or role or where the item can wait. Fewer steps hide waits, while many more make the map hard to read. The board accepts at most 50 steps.
What do I do after the value stream analysis?
The team picks the longest wait and collects ideas to shorten it, for example fixed time slots, fewer handovers or clear ownership. Then it changes one thing and measures again. The CSV file records the state. Comparing lead time before and after the change shows whether the measure worked.

Sources

  • Mike Rother, John Shook: Learning to See: Value Stream Mapping to Add Value and Eliminate Muda (1999)