Risk Matrix

A risk matrix places risks on a grid of five by five fields by likelihood and impact. The product of both values gives the risk score from 1 to 25 and with it the level low, medium, high or critical. The team records the risks together in real time and sets a mitigation and an owner for each one. The list next to the grid sorts all risks by score in descending order.

How it works

  1. Create a board and share the link with the team.
  2. Enter risks with a title and pick likelihood and impact from 1 to 5.
  3. The matrix shows each risk with its ID in the matching field.
  4. Agree on mitigations and owners for the risks with a high score.
  5. Download the result as CSV.

When should you use a risk matrix?

A team uses a risk matrix when several possible problems are on the table and it has to decide which to address first. Typical occasions are the start of a project, release planning, a migration with a hard deadline or the regular risk review in a running initiative. The matrix turns an unstructured list of worries into a ranking that everyone can follow.

It is less suited when a risk has already occurred. At that point the team faces a problem to solve and no longer an estimate. Hazards with health or safety consequences also need more than two estimated values, because standards and specialist procedures apply there. For alignment in project and product teams, the 5x5 matrix is a common and quickly understood tool.

How do you calculate risk score and risk level?

The risk score is the product of likelihood and impact, which the team rates on a scale from 1 to 5 each. A 1 stands for very unlikely or hardly noticeable, a 5 for very likely or severe. This gives scores from 1 to 25. Because only products of two numbers from 1 to 5 are possible, scores like 7, 11 or 17 do not occur.

The levels follow a common split of the 5x5 matrix. Scores from 1 to 4 count as low, 5 to 9 as medium, 10 to 16 as high and 20 to 25 as critical. No value exists between 16 and 20, so there is no gap. The fields of the matrix are colored by their level.

On this board each risk also has a title, a mitigation and an owner. The board assigns the IDs R1, R2 and so on in the order of entry. The list next to the matrix sorts all risks by score in descending order.

What does a risk matrix look like in practice?

The example is invented. A team plans the rollout of new accounting software and rates seven risks. The table shows them in the order the list on the board uses. A score of 12 can come from 3 times 4 or from 4 times 3. The team therefore chooses the mitigation by cause and not by number alone.

IDRiskLikelihoodImpactScoreLevel
R3Budget approval is delayed4520critical
R1Supplier interface arrives late4312high
R2Project lead is out for weeks3412high
R5Data migration produces wrong balances2510high
R4Requirements change along the way428medium
R6Test environment goes down155medium
R7Training date collides with quarter close224low

How do you facilitate a risk assessment with a team?

A risk assessment takes about an hour with a clear sequence. In a remote setting one person opens the board and shares the link. Everyone enters risks at the same time and the list re-sorts after every entry. One person moderates and makes sure each value is explained briefly.

  • Collect risks first without rating them. A risk describes a possible event and its consequence, for example delivery slips and testing starts later.
  • Rate together afterward. When two people are far apart, each explains their number before you agree on a value.
  • Agree beforehand what a 1 and a 5 mean for impact, for example in days of delay or in dollars.
  • Discuss the risks from top to bottom. Clicking a field of the matrix filters the list to the risks in it.
  • Enter a mitigation and an owner for every high and critical risk before you end the meeting.
  • Schedule a follow-up meeting to review the values again.

What mistakes happen in risk assessment?

The most common mistake is rating by gut feeling without a shared scale. One person reads impact 5 as total failure, another as a one week delay. Agree on common yardsticks at the start and write them into the project notes.

A second mistake is leaving risks without a mitigation and an owner. A list without ownership only documents worries. A third mistake is treating the assessment as a one-off meeting: likelihood and impact change during a project. A risk that is low today can turn critical when the situation shifts.

Finally, the product invites false precision. A risk with score 12 is not exactly twice as bad as one with score 6. The score puts risks in an order and does not measure anything. For rare events with severe consequences a second look pays off even when the score comes out medium.

Risk matrix or FMEA: what is the difference?

The risk matrix rates risks with two values, while FMEA classically rates failure modes with three. FMEA (failure mode and effects analysis) comes from product development and manufacturing. It multiplies severity, occurrence and detection into a risk priority number. For projects and product teams the matrix is quicker to set up.

AspectRisk matrixFMEA
Rated valuesLikelihood and impactSeverity, occurrence and detection
ResultScore from 1 to 25 with four levelsRisk priority number
Typical subjectProject, product and schedule risksFailures of a product or process
EffortOne sessionSystematic analysis per component
PresentationGrid with colored fieldsTable

Key terms

Risk
A possible event that has not occurred yet and would hurt the goals of an initiative if it did.
Likelihood
The estimate of how probable it is that a risk occurs. Here on a scale from 1 to 5.
Impact
The extent of the consequences if a risk occurs. Here also from 1 to 5.
Risk score
The product of likelihood and impact. On this board between 1 and 25.
Mitigation
An action that lowers the likelihood, limits the impact or absorbs the consequences.
Risk owner
The person responsible for a risk and its mitigation. On the board this is the owner field.

Frequently asked questions

What is a risk matrix?
A risk matrix is a grid on which a team places risks by two properties: how likely an event is and how strong its impact would be. Both values range from 1 to 5 here. Their product is the risk score. The higher the score, the more urgently the risk needs a mitigation. The matrix shows this ranking at a glance.
How are the risk score and the level calculated?
The risk score is likelihood times impact and lies between 1 and 25. Scores from 1 to 4 count as low, 5 to 9 as medium, 10 to 16 as high and 20 to 25 as critical. This split is common for matrices with five by five fields. The fields of the matrix are tinted in the colour of their level.
Can several people work on it at the same time?
Yes. Everyone who opens the link sees the same state in real time. Participants add risks, change values and texts and delete entries. Anyone who joins as an observer sees the board but cannot change it. The role can be switched in the room at any time. No sign-up is needed, a name is enough.
Are the risks saved?
The risks are only kept in the room on the server. As soon as everyone has left, the room is deleted after a short time and all entries with it. That is why there is the CSV download. The file contains ID, risk, likelihood, impact, score, level, mitigation and owner and opens in Excel.
How do I use the risk matrix in a project?
A common pattern is a session at the start of a project in which the team collects and rates risks. It then sets a mitigation and an owner for the risks rated high and critical. In later sessions the team checks the values again and adjusts them. Clicking a field of the matrix filters the list to the risks in it.
How many risks belong in a risk matrix?
Fifteen to thirty risks are usually enough for a project. More important than the count is that each risk describes a concrete event, that the team can rate it and that every high risk has a mitigation. The board accepts up to 100 risks. The team clears out older entries that no longer fit the current situation on a regular basis.
What is the difference between a risk and an issue?
A risk is a possible event in the future, while an issue has already occurred. For a risk the team rates likelihood and impact and plans precautions. An issue needs a solution and an owner. When a risk occurs, the team removes it from the matrix and continues it as a task.
What do I do about risks I cannot prevent?
A team can avoid, reduce, transfer or consciously accept a risk. If it cannot be prevented, you limit the impact, for example with a contingency plan. Insurance shifts it to a third party. Accepting means that the owner knows the decision and notes as a mitigation when the risk will be reviewed again.
How often should you review the risk matrix?
The team reviews the matrix at fixed intervals, for example every two weeks or at each project phase. When the situation changes, an extra meeting pays off, for instance after a team member drops out or a deadline moves. On the board you change values and mitigations at any time. The list and matrix update immediately.
Why is there no risk score between 16 and 20?
The risk score is a product of two whole numbers from 1 to 5. No such product equals 17, 18 or 19. The possible scores are 1, 2, 3, 4, 5, 6, 8, 9, 10, 12, 15, 16, 20 and 25. The levels high and critical therefore meet without a gap.
Can I share the risk list with third parties?
Yes, through the CSV download. The file contains ID, risk, likelihood, impact, score, level, mitigation and owner and opens in Excel. Keep in mind that risk texts often hold assessments about people or suppliers. Review the content before you share the file.